Tekran Denuder and Particulate Heating Check

 

Purpose:  The Tekran denuder module and particulate module have heaters that need to be checked from time to time.  This procedure shows the process for checking the integrity of the heaters.

 

Required Equipment:  NONE

 

Reference:  SOPMAN

 

 

Heat Controller Efficacy

 

1.        In the denuder module there are four heat controllers (PID).  In the particulate module there are three PIDs.  Observe each controller to make sure the LED on each is working.

2.        Both the denuder module and the particulate module have external power cables.  DO NOT confuse this cable with the umbilical from the shelter. 

3.        If the controller isn’t working check the GFI (Ground Fault Interrupter) for each unit.

4.        If the GFI has been tested and reset check the breaker in the breaker box.  The breaker may look like it is OK but it should still be shut off and then back on.

5.        The two previous steps should have fixed the issue.  If not call Plano for assistance.

 

Heat Controller Programming

 

1.        Now that the controllers are working, the programming needs to be checked.

2.        This can be done with the Tekran in run mode.

3.        Find out what heating sequence the Tekran is in and observe the controllers.

4.        The three sequences that should be noticed are when the denuder is heating, the RPF is heating and when the pyrolyzer is heating.  The final temperature should be noted.

5.        Other controllers to check will be the external heater temperature, sample line temperature and the case temperatures.  For this group of controllers the temperature is constant.   

6.        If any of the sequences or temperatures are not working call Plano for assistance.